¡¡¡¡¡ñThe overall planning objectives of infrastructure
¡¡¡¡The detailed planning on the municipal projects and utilities
project at the first phase of Tianjin Lingang Industrial Area is
based on the social, economical development of Lingang Industrial
Area in different stages as well as the enterprise development and
offers the powerful guarantee for the important stage of development
of Lingang Industrial Area at the beginning of the new century.
Statistic Table on the infrastructure and
scale
 |
Sum
total for the first stage |
| Road area
£¨10,000 m2 £© |
191.45 |
| Water
supply |
For production
use (10,000 m3/d) |
20.00 |
| For life use
(10,000 m3/d) |
20.00 |
| Pipe network for water supply
(km) |
121.55 |
| Pipe network for drainage (km) |
101.48 |
| Sewage disposal ability (10,000
m3/d) |
14.00 |
| Reclaimed water treatment ability
(10,000 m3/d) |
1.68 |
| Fuel gas (10,000 m3/d) |
535.60 |
| Pipe length for power supply (km) |
22.30 |
| Electric power (10,000 kw) |
72.78 |
| Pipe length for power supply (km) |
75.00 |
| Program Controlling Exchangers
(10,000 sets) |
2.00 |
| The length for telecommunication
pipeline: optical cables and cables£¨km£© |
860 |
| Green area£¨10,000 m2£© |
176.00 |
¡¡¡¡¡ñthe first phase overall planning --- Planning target on infrastructure
¡¡¡¡¡ø Roads
¡¡¡¡There are total 3 arterial highways, 4 secondary arterial highways
and several branches during the first stage. In this area, there
are 9 bridges under planning. So far, the temporary roadbed finished
in Lingang has reached 24 kilometers and the construction on No.4
Planning Road has formally began in April 2005.
¡¡¡¡¡ø Railway
¡¡¡¡The railway construction will start from East Dagu Compiling
Station and extend into Tianjin Lingang Industrial Area along with
the South Drainage River. There will be two railways starting at
the west along No.16 Road and south along No.3 Road with an arrangement
station will be built to the west of No.16 Road. Now, Tianjin Local
Railway Bureau has been entrusted to work out a detailed plan and
it is estimated that the railway will formally put into operation
and extend to Lingang by 2006 and the transport capacity shall reach
ten million tons per year.
¡¡¡¡¡ø Wharf and Tank Farm
¡¡¡¡Lingang Industrial Area Harbor Affairs Co., Ltd. has been established
and has planned to build up one liquid wharf at 5,000-tonnage and
a bulk cargo wharf at 20,000 tonnage by the end of 2005 as well
as a 50,000-tonnage wharf by 2006. The tank farm is under construction
and another large-scaled petrochemical tank yard has planned to
be constructed.
¡¡¡¡¡ø Water supply
¡¡¡¡By the end of 2005, the water-supply capability for Tianjin Lingang
Industrial Area shall be able to reach 50,000 tons per day, and
up to 2008, both Tanggu Municipal Running Water and Beitang Industrial
Water Works will be able to provide 100,000 tons of water for the
area per day. By the year of 2020, Tianjin Lingang Industrial Area
shall receive 200,000 tons of water for daily use and the Tanggu
Seawater Desalinization Plant will shall also be capable of supplying
200,000 tons of water per day.
¡¡¡¡¡ø Wastewater treatment
¡¡¡¡Tianjin Lingang Industrial Area will build up Wastewater treatment
plant by the way of the joint venture, raising the funds as well
as the general contract. The Wastewater treatment plant within Tianjin
Lingang Industrial Area is designed to dispose of 140,000 tons of
wastewater per day and the secondary Wastewater treatment plant
can deal with 16,800 tons per day, it is predicted that such plant
shall formally come into operation by the year of 2008.
¡¡¡¡¡ø Electricity Power
¡¡¡¡In April 2005, one 35KV transformer substation shall be built
to meet the need for construction work. At the beginning of 2006,
the first 220KV transformer substation shall has been completed
and the heat and power plant project will formally put into construction.
¡¡¡¡¡ø Telecommunication
¡¡¡¡The construction of telecommunication network at the first phase
shall help realize the economic and social informationization of
Tianjin Lingang Industrial Area enabling it to become one window
opening to the outside world for the purpose of promoting the economic
development.
¡¡¡¡¡ø Natural gas
¡¡¡¡The pressure of planned gas source of Lingang is designed to
be within the range of 0.4-2.5Mpa and the gas volume supplied during
the first phase shall be 140,000 cubic meters per hour.
¡¡¡¡¡ø Pipe rack
¡¡¡¡North-south main pipeline work will be along the west side of
No.19 Planning Road and No.21 Planning Road. To ensure the smooth
connection of pipeline, the arterial pipe work will be built to
the east of No.6 Planning Road and No.20 Planning Road and the secondary
arterial pipe work will lined to the west of No.6 Planning Road.
¡¡¡¡¡ø Fire control
¡¡¡¡The responsibility zone of firehouse in chemical industrial area
is in Class A. Total four first-class firehouses shall be set up
in the planed area at the first stage in Tianjin Lingang Industrial
Area, amongst one special firehouse and three normal ones, which
is situated an the center of responsible field with convenient traffic
condition.
¡¡¡¡¡ø Industrial gas
¡¡¡¡An international gas supplier shall make the investment in this
field and shall complete the project introduction work before June
2005. The plant starts to offer all kinds of industrial gas to the
enterprises within Tianjin Lingang Industrial Area by the end of
2006.Up to 2009, the gas supply volume shall reach 100,000 cubic
meters per day.
¡¡¡¡¡ø Administration Center
¡¡¡¡An administration center shall be built to the south of Tianjin
Lingang Industrial Area that offers all-round and " one-stop
type " service for all the enterprises in the area.
|